OUR HYDROELECTRIC POWER PLANTS
MERAL ELECTRICITY PRODUCTION INC.
ESENDURAK HYDROELECTRIC POWER PLANT - ERZURUM
The Esendurak Hydroelectric Power Plant project is located in the Eastern Anatolia Region, within the boundaries of Tortum District, Erzurum Province. The water source of the project is provided by the Alapınar Stream, which is a tributary of the Tortum Stream, one of the side branches of the Çoruh River
Esendurak HPP has obtained a production license for 46 years. It is a river-type power plant. The capacity of the regulator and the downstream facilities built on the Alapınar Stream is determined and projected to be 5.00 m³/s.
The Esendurak Hydroelectric Power Plant has an installed capacity of 9.52 MW and an annual production capacity of 42.421 GWh/year. The plant started producing energy on 10.10.2012 and continues to operate.
PRODUCTION DETAILS
- Installed Capacity: 9.46 MW
- Regulator Structure and Sedimentation Pond
- 2,800 m Transmission Pipe Q=2400 mm
- Esendurak - Alapınar Tunnels 4m (400m+600m)
- 2,500 m U-shaped Transmission Channel
- Loading Pond: 300 m
- Full Spillway, Bottom Spillway Drainage Channel: 720 m
- Water Intake Structure
- Centrifugal Pipe Construction Works
- Power Plant Building
- Energy Transmission Line: 24 km
ARTVİN ENERGY ELECTRICITY PRODUCTION INC.
BUCUR HYDROELECTRIC POWER PLANT - ARTVİN
The Bucur Hydroelectric Power Plant project is located within the boundaries of Artvin Province.
The plant's current installed capacity is 3.13 MW, with an expected total energy production of 17,340 GWh.
Bucur HPP is in the process of obtaining a license from the Energy Market Regulatory Authority (EPDK).